Street Resurfacing Projects

Arterial, residential and the Main Street reconstruction project will all begin, weather permitting, on May 29, 2018.

Main Street from 15th to 17th Avenue will begin on May 29, 2018.

1st Phase - construction will be on the east side of the intersection of 16th Avenue and then on the east side of Main Street from 15th north to 17th Avenue.  This will include tree removal and new curb and gutter.  

The 17th and Main intersection will be closed completely for two weeks from June 11th to June 18th, weather permitting.  

residential streets

Contractor - Circle C, will begin on 23rd to 30th and Main to Monroe.

arterial streets

Contractor - APAC will begin milling and resurfacing at the south end of Airport Road.  This construction will use a pace car for traffic during lane closure.